2026 Update
We are excited to share the progress of our building remodel. As of January 2026, we have made significant strides towards our big picture goals.
Phase I of our remodel is now complete: we have installed an 800 amp electrical service, HVAC, a freight ramp, completed interior demolition and buildout for pallet capable warehouse space with LED lighting, purchase of an electric pallet jack and completion of a walk- in freezer and walk-in refrigerator!
Phase II of the remodel will include interior re-wiring to accommodate new refrigeration and office/meeting space, eliminate out of date fuse boxes, build out office/meeting space/volunteer break room, new janitorial space with commercial sink, build out for “client choice” pantry and sound insulation to block pantry noise in the church!
Keep reading for installation pictures and the remodel plans.
We Started Our Remodel Project in 2025
In 2025, we initiated a total remodel of our space in the St. Anthony Church basement.
This ambitious project will include a total overhaul and restructuring of the basement, including: new electrical service, central HVAC, a freight door, centralized warehouse storage space.
We are so very grateful to those of you who have contributed in so many ways, which has allowed us to start to remodel. More help is needed to finish the project.